Priority School Building Programme PSBP
The Priority Schools Building Programme (PSBP) was established in 2011 to address the needs of those schools in the worst condition that required urgent repair. The programme is centrally managed and procured by the Education & Skills Funding Agency (ESFA), an executive agency, sponsored by the Department for Education (DFE).
Making sure schools are high quality and positive environments is a key part of the government’s long-term vision for education. There is a general belief that better schools help build a fairer society and a better economy. The intention of the Priority Schools Building Programme is to undertake school rebuilding and refurbishment projects to improve the overall standard of school buildings by creating classrooms which are conducive to learning and providing access to world-class facilities for pupils and teachers.
The programme covers primary, secondary and special education needs (SEN) schools. The list of 261 schools that were successful in the first phase of the programme was announced in May 2012, covering schools due to be wholly or substantially rebuilt by 2017. 215 of these schools are being delivered by capital grant funding and 46 schools via private finance funding.
Schools in the programme are spread across England and have been grouped together in batches by taking consideration of condition, need, commercial viability and geography.
A number of consultants have been appointed to deliver the PSBP and many contractors submitted bids to secure the construction contracts, as well as ongoing maintenance contracts. Companies listed on the EFA contractors framework were invited to bid for each of the capital batches. The bids were reviewed and evaluated and 2 contractors shortlisted. Following a further period of competition the successful contractors were appointed.
As of 26 January 2015, 16 schools had been completed and 55 schools were under construction. The remaining projects were deep into the planning or development stages.
The government believes that schools are being developed much faster and cheaper under the PSBP than those developed under the previous school building initiative, Building Schools for the Future (BSF). It took around 3 years for construction work to begin under the BSF, whereas under the PSBP this has been reduced to 1 year. PSBP projects are thought to have cost around a third less.
In May 2014 the government announced a further £2 billion for a second phase, PSBP2, which will undertake rebuilding and refurbishment projects across 277 schools from 2015 to 2021. In February 2015, an extra £4 billion was allocated between 2015 and 2018. Deputy Prime Minister Nick Clegg said, “...it is crucial that we invest in education, so that every child has a fair start in life”. Ref Gov.uk, £6 billion investment to rebuild and improve schools across England, 9 February 2015.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Baseline designs for schools.
- Building Bulletin 93: acoustic design of schools
- Building Schools for the Future.
- Free schools.
- House of Commons, Treasury - Seventeenth Report: Private Finance Initiative.
- Independent Client Advisers.
- Major Projects Authority.
- OGC.
- PF2
- PFI
- Public private partnership
- Public procurement.
- RIBA client adviser.
Featured articles and news
Key points for construction at a glance with industry reactions.
Functionality, visibility and sustainability
The simpler approach to specification.
Architects, architecture, buildings, and inspiration in film
The close ties between makers and the movies, with our long list of suggested viewing.
SELECT three-point plan for action issued to MSPs
Call for Scottish regulation, green skills and recognition of electrotechnical industry as part of a manifesto for Scottish Parliamentary elections.
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.